Possession-Linked Payment Plans: The Fine Print That Can Bite You
Plans like 50:25:20:5 sound buyer-friendly, but the trigger conditions for each tranche matter more than the ratio itself.
The Pain Point
A payment plan structured around construction milestones can be gamed — developers sometimes demand the next tranche the moment a slab is poured, regardless of whether prior work meets quality or timeline expectations, leaving buyers little leverage to withhold payment.
The Fix
Read the exact milestone definitions in the builder-buyer agreement, not the marketing brochure. Insist on photographic or third-party progress verification before releasing milestone payments, and know that RERA gives you the right to withhold payment if construction doesn't match the demand stage — most buyers don't realize this leverage exists until it's too late.